Bellevue Public Works Department Releases Updated Construction Schedule for 36th Street Project.

The City of Bellevue's Public Works Department has released the updated construction schedule for the upcoming 36th Street project. This total project includes improvements and lane widening on 36th Street from Bline Avenue on the North to Platteview Road on the South. The first phase of this project will involve 36th Street between Bline Avenue to Sheridan Road. 

Here is the current project schedule:

FHWA approves Draft Environmental Assessment (DEA) – July 2016

Public Hearing – August 2016

FHWA approves Errata – November 2016

City Final Design Request for Proposals (RFP)/Selection/Contracting – March 2017

NDOR reviews & Approves 90% Design for Right of Way (ROW) – August 2017

ROW Process – August 2017 thru October 2018

Plans Specs & Estimates (PS&E) turn-in – October 2018

Letting – Jan 2019

Potential Construction Start – Spring 2019

 

Please contact the City of Bellevue Public Works Department at 402-293-3025 for more information.

 

 

Print
0 Comments
Rate this article:
4.1

Categories: AnnouncementsNumber of views: 12458

Tags:

x
«July 2025»
MonTueWedThuFriSatSun
30123456
78910111213
14151617181920
21222324252627
28293031123
45678910

Archive